On Thursday, 08.07. we celebrated together with craftsmen, friends and neighbors the topping. Last Friday, the Carpenters continued working on the roof.
We also had yesterday set a two hour appointment with the electrician for the electrical design in detail. The offer for the additional services we receive early next week.


In the next two weeks (28 and 29 KW) are plumbing run + it is the roof (to be completed until July 22).
also next Tuesday (13.07.) Are the windows and Exterior doors. So that we can continue to visit our house, we have already received mail from our construction manager a house key to the locksmith.