Today was erected a scaffolding around the house. In addition, all interior walls are brick (about 80% of the final height).




was also sent to us yesterday evening via e-mail site manager of the mandatory schedule for all other trades. This is such that the final building inspection by us in the KW38 (more precisely, on Thursday, 23.09) will take place.
dates for the next week (27 KW / 5:07 to 11:07.)
Mon - Fri install window Masonry (ie latching)
Thurs Point + site visit site management
Fri
Hurra, so that we can already at Thursday topping celebrate + should now begin planning for the topping including inviting friends and acquaintances ...