Thursday, July 29, 2010

Master Chief Halo Yaoi

interior window sills and electrical / plumbing

In the last four days, a lot has happened: There were up to 10 workmen for three trades drywall, electrical and plumbing while working and the day of morning until late in the evening (sometimes until 21.00 or even 22.00 clock)!

The dry construction was completely finished - Covering of the ceiling and create the interior walls in both bathrooms. In Elternbad the interior walls in T version was created (the sink front, left behind the wall of the large shower in 110cm width and right behind the wall of the toilet).

day another company must also have been on site to the interior window sills (agglomerate marble) used.

The body-in installation work Electrical and plumbing are already far advanced and will be finalized tomorrow.

distributor floor heating


plumbing and interior wall children's


clutter






living room ceiling and floor flap



Elternbad: Interior walls in T-version


Monday, July 26, 2010

Where Can I Buy Reborn Kits

Drywall & body shop installation Electrical / Plumbing / Heating

be parallel in this week's dry interior construction as well as the body shop installing electrical and heating / plumbing run.

Already at the end of the first day were all insulated ceilings + In some rooms already have the electrical boxes milled in the wall.

As can be seen on the pictures, the end of last week was also creates the Sohlenabklebung, that is the floors on the ground floor and basement have been glued with bitumen (diffusion barrier).

Insulation ceiling living / dining

insulation ceiling hallway


Electric raw installation and Sohlenabklebung






stairs to the attic

Thursday, July 22, 2010

Pubic Hair In The Underwear

roof tiles roof tiles

this evening the roof was covered completely, ie also including east and south side of First and pans.


Tuesday, July 20, 2010

What Does Mount As Virtual Disc Mean

Part 2 Part 1

was now stocked up on the south side of the house with tiles.


Monday, July 19, 2010

Modify Brookstone Helicopter

gutters

were now mounted gutters and downpipes.



early as last Friday, the roof tiles have been delivered and posted directly to the crane on the roof.



should the roof be covered with tiles in the coming days. Moreover, in the house to the concrete floors are covered with tar paper (diffusion barrier).

According payment plan so that we reach the end of the week the status of construction site ready. "

Thursday, July 15, 2010

Milena Velba At Nurse

Traufgesimse

be Today and Tomorrow created the roof overhangs, ie the so-called attached Traufgesimse.





This weekend we will glaze the Trausgesimse and smooth edges of boards twice in self-work white.

Tuesday, July 13, 2010

Free Pokemon Jar Games

installation window

This week (week 28) will continue the roofing & Present also were the windows and exterior doors installed.

main entrance


side entrance





Chart Of Numering System



release of our project on Detailx:

http://www.detailx.de/hochschulen/hochschulnews/archiv/koih-cube/

Saturday, July 10, 2010

Mineral Makeup Images

17.-18. Day - roof / topping / Electrical Design

On Thursday, 08.07. we celebrated together with craftsmen, friends and neighbors the topping. Last Friday, the Carpenters continued working on the roof.

We also had yesterday set a two hour appointment with the electrician for the electrical design in detail. The offer for the additional services we receive early next week.





In the next two weeks (28 and 29 KW) are plumbing run + it is the roof (to be completed until July 22).

also next Tuesday (13.07.) Are the windows and Exterior doors. So that we can continue to visit our house, we have already received mail from our construction manager a house key to the locksmith.