find Since Tuesday, the tile work place (wall and floor tiles, floor tiles and EC Keller). Completion of the tile work is done by the end of next week (03.09.). Since
Wednesday are also the artists in action: Prime ceilings and walls, ceiling, wall paper and painting, painting walls, stucco sills, etc. The painting will need two weeks and completed by mid-KW36 (07./08.09.).